News On Projects
Products & Services
Projects Database
Tenders Database
E - Newsletter
EPXonline.com
Project Financing
Contracts & Awards
Energy
Electricity
Mining
Oil & Gas
Infrastructure
Airport
Port
Railway
Road
Freezone
Construction
Manufacturing
Cement
Engineering
Automobile
Plastic
Metal
Textile
Paper & Packaging
Leather
Sugar
Edible Oil
Electrical & Electro
Processing
Chemical
Drugs & Pharma
Fertiliser
I-C-T
Communication
IT
Telecom
Water
Pump Station
Water Treatment
Water Supply
Hospitality
Hotel
Restaurant
Resort
Entertainment
Sports
Multiplex
Theme Park
Food & Beverages
Hospital
Service
Social
Science
Irrigation
Government
Policy
Economic Indicators
Company News
Commerce
Miscellaneous
News Uploaded On : Tuesday, May 17, 2016 1:02:00 PM IND Back  |  Latest Projects  |  Latest Tenders
 
 E-mail this to a friend        Printable version       Story Viewed 1659 Times
Bhilai steel plant Rs. 17,000-cr expansion delayed by 15 mths.
Even as the Steel Ministry races to complete Rs 61,870-crore modernisation and expansion, the process at Bhilai Steel plant (BSP), the largest facility of the state-run giant SAIL, has been delayed by 15 months.

BSP's modernisation and expansion plan, which entails an investment of Rs 17,266 crore, raising steel capacity from 3.93 million tonnes per annum (MTPA) to 7 MTPA, has been delayed as SAIL had to terminate contracts twice due to "unsatisfactory performance", sources said.

The flagship plant of the Maharatna firm is installing two rolling mills for production of high quality long rails (260 m length) and bars as well as is phasing out old and energy inefficient process routes for reducing carbon foot print and cost of production.

Initially, the programme was expected to be completed by September 2015, which was later revised to October 2016. It has now again been revised to December 2016, a 15-month delay from original completion schedule, sources said.

"BSP first hired Ratna Infra for its steel melting shop (SMS) package, which had to be terminated due to slow progress of work and fresh contract was awarded to state-run Hindustan Steelworks Construction (HSCL) HSCL at risk and cost of Ratna Infra," they said.

However, HSCL's contract also had to be terminated due to poor progress and this had to again be given to Simplex at risk and cost of HSCL, which is the main reason behind the delay of the modernisation and expansion programme.

When contacted on the change in contractors, a SAIL spokesperson said: "The contractors were changed because of their unsatisfactory performance."

On the completion date of the programme, he said: "The completion of modernisation and expansion at BSP is envisaged in December 2016."

Some of the facilities have been completed and balance facilities are under various stages of execution and all efforts are being made to complete the balance facilities progressively as per the target date, he said.

Sources also said that "The equipment erection package also had to be re-tendered as sufficient erection fronts could not be handed over within contractual completion period and a fresh contract was awarded to Essar Projects.

"Also state-owned Heavy Engineering Corporation's slow progress of work on installation of cranes for both equipment erection and subsequent material handling during production impacted the programme."

SAIL is in process of enhancing its hot metal production capacity to 23.46 MTPA and crude steel to 21.04 MTPA under its current phase of expansion and modernisation which is expected to be completed by 2016-17 fiscal, ending March 2017.

The indicative investment is about Rs 61,870 crore. The cumulative expenditure until December 2015 has been Rs 61,245 crore including expenditure of Rs 4,482.83 crore during the 2015-16 fiscal till December.

TOI

Post your comments:

Your name: *
E-Mail Id:
E-mail ID will not be published
Comment: *
Maximum 500 Characters
    
Related Stories
Gujarat: Adani Enterprises to set up 1 million tonne copper plant in Mundra.
APL Apollo Tubes to set up manufacturing plant in Chhattisgarh.
Steel Strips Wheels opens steel processing unit
Uttam Value Steels gets green nod for Rs 3,325-crore expansion.
ArcelorMittal exits steel mill in Karnataka, moots solar farm instead.
Odisha steel project: Posco needs to file fresh proposal
Srijan Steel gets green nod for Rs. 256 crore greenfield iron ore project.
NMDC set to commission Karnataka pellet plant in Q3
Visvesvaraya steel plant revival.
Posco signs deal to set up steel plant in Maharashtra.
RELATED PROJECTS & TENDERS
ADVERTISEMENT
MOST POPULAR STORIES NOW
For all enquiries please contact
Tel: 022 - 25961254, 25960909
Mobile: 9821464666/09751178830
Mail: marketing@newsonprojects.com

OUR OTHER PRODUCTS & SERVICES:    Projects Database   |   Project e-Newsletter   |   Tenders Database   |   Commissioned Power Plants   |   Company Index
About Us   |   Contact Us   |   Terms of Use   |   Advertise with Us   |   Privacy Policy   |   Disclaimer   |   Feedback