News On Projects
Products & Services
Projects Database
Tenders Database
E - Newsletter
EPXonline.com
Project Financing
Contracts & Awards
Energy
Electricity
Mining
Oil & Gas
Infrastructure
Airport
Port
Railway
Road
Freezone
Construction
Manufacturing
Cement
Engineering
Automobile
Plastic
Metal
Textile
Paper & Packaging
Leather
Sugar
Edible Oil
Electrical & Electro
Processing
Chemical
Drugs & Pharma
Fertiliser
I-C-T
Communication
IT
Telecom
Water
Pump Station
Water Treatment
Water Supply
Hospitality
Hotel
Restaurant
Resort
Entertainment
Sports
Multiplex
Theme Park
Food & Beverages
Hospital
Service
Social
Science
Irrigation
Government
Policy
Economic Indicators
Company News
Commerce
Miscellaneous
News Uploaded On : Friday, October 06, 2017 10:23:00 AM IND Back  |  Latest Projects  |  Latest Tenders
 
 E-mail this to a friend        Printable version       Story Viewed 3518 Times
GE completed first phase of Champa-Kurukshetra power super highway.
GE T&D India, one of the largest players in the power transmission and distribution value chain, and a part of US giant General Electric (GE), have announced commissioning of the first 1,500 MW phase of the two-phased Champa-Kurukshetra high-voltage direct current (HVDC) power transmission system in Chhattisgarh. The company was contracted by the Power Grid Corporation of India Limited (PowerGrid) at the cost of about ₹3,000 crore.

The first pole of 1,500 MW power was commissioned in March 2017 while the second pole of same capacity was commissioned this month - four month later than the initial target of June 2017. According to Power Ministry, the total cost of two-phase project is ₹6,300 crore.

The transmission system will further be upgraded to 6,000 MW capacity with addition of second HVDC bipole of 3,000MW at an additional cost of about ₹5,200 crore. The additional phase is expected to be completed by December 2018.

Being GEís first 800 kV UHVDC project worldwide, Champa-Kurukshetra link is a 1,287 Km energy highway aiming to transmit power of upto 3,000 MW through HVDC Interconnector Transmission.The power highway will enable transfer of power from IPP generation projects coming up in Raigarh, Champa, and Raipur generation complex in Chhattisgarh to demand centres of Northern region viz. Haryana, Punjab, UP, Rajasthan and adjoining areas.

HVDC is the preferred solution for bulk electrical transmission over long distances as it allows transmitting up to three times more power over long distances than traditional alternating current transmission.The project, according to GE, is globally the first 800 kV scheme to use dedicated metallic return conductors that eliminates the need for ground electrodes, thereby increasing the systemís reliability.

ďAs India makes progress towards achieving sustainable, universal access to electricity, an efficient mix of conventional and renewable power, along with strengthening of the inter and intra-state power evacuation system is required,Ē Vishal Wanchoo, President & CEO of GE South Asia said commenting on the development. Champa-Kurukshetra line could serve as a model for taking the benefits of the digital grid to the masses, he added.

GE T&D India, formerly Alstom T&D India (GE completed the acquisition of Alstomís power and grid businesses in over 20 countries in 2015) posted a net profit of ₹61 crore for the first quarter ended June 30, 2017 against net loss of ₹197 crore in the year-ago period. Its order intake in the first quarter of this fiscal has increased almost 100 per cent to ₹15,811 crore compared to ₹7,956 crore in the Q1 FY17. Overall order backlog reported by the company earlier this year stood above ₹84,000 crore.

HBL

Post your comments:

Your name: *
E-Mail Id:
E-mail ID will not be published
Comment: *
Maximum 500 Characters
    
Related Stories
SCCL power plant PLF eighth best.
Power sector's first InvIT IndiGrid acquires 3 more projects at Rs. 1,490 cr.
Solar power capacity goes up to 2,275 MW.
Vikram Solar commissions 80-MW plant in Gujarat.
New norms for solar power projects bidding good for sector: ICRA.
ECIL sets up rooftop solar plant at its Hyderabad factory.
GJ Nature Care, GJ Eco Power to set up waste-to-energy projects.
Ocean Research Institute installs rooftop solar plant
Floating solar power plant.
Premier Solar sets up 200 MW solar module facility in Telangana.
RELATED PROJECTS & TENDERS
ADVERTISEMENT
MOST POPULAR STORIES NOW
For all enquiries please contact
Tel: 022 - 25961254, 25960909
Mobile: 9821464666/09751178830
Mail: marketing@newsonprojects.com

OUR OTHER PRODUCTS & SERVICES:    Projects Database   |   Project e-Newsletter   |   Tenders Database   |   Commissioned Power Plants   |   Company Index
About Us   |   Contact Us   |   Terms of Use   |   Advertise with Us   |   Privacy Policy   |   Disclaimer   |   Feedback