News On Projects
Products & Services
Projects Database
Tenders Database
E - Newsletter
EPXonline.com
Project Financing
Contracts & Awards
Energy
Electricity
Mining
Oil & Gas
Infrastructure
Airport
Port
Railway
Road
Freezone
Construction
Manufacturing
Cement
Engineering
Automobile
Plastic
Metal
Textile
Paper & Packaging
Leather
Sugar
Edible Oil
Electrical & Electro
Processing
Chemical
Drugs & Pharma
Fertiliser
I-C-T
Communication
IT
Telecom
Water
Pump Station
Water Treatment
Water Supply
Hospitality
Hotel
Restaurant
Resort
Entertainment
Sports
Multiplex
Theme Park
Food & Beverages
Hospital
Service
Social
Science
Irrigation
Government
Policy
Economic Indicators
Company News
Commerce
Miscellaneous
News Uploaded On : Friday, March 09, 2018 10:48:00 AM IND Back  |  Latest Projects  |  Latest Tenders
 
 E-mail this to a friend        Printable version       Story Viewed 933 Times
Vizhinjam port project: Major segments hit; Phase I to be delayed.
That the Vizhinjam port project would miss the 1,000-day deadline set by Gautam Adani is now official with the state government making admissions to that effect in the Assembly. The way things are shaping up, the project is also likely to miss the contractual deadline of 1,460 days for commissioning Phase I.

Major glitches in rock supply had hit the construction of the breakwater months ago. Now dredging work - the second of the three big components in Phase I - has also come to a standstill. Work on both segments is expected to resume in full strength only after the southwest monsoon.

The Adani Group has not succeeded in replacing the two dredgers that were damaged in Cyclone Ockhi in November-end. It is now almost certain the group will have to give a miss to the current dredging season.

Sources said, full-fledged dredging is expected to resume only by October this year. Dredging will prove impossible by May with the seas turning rough due to the monsoons.

‘’We will be hard-pressed,’’ is how a senior Adani Group official responded to a query as to whether it would be able to meet the contractual deadline of December 4, 2019.As per the concession agreement signed between the state government and the Adani group, Phase I would consist of 800 metres of berths and the breakwater. The dredging of the channel also was expected to be completed by then. Commercial operations, as per an earlier announcement made by the state government, was to start on December 5.

The 1,000-day deadline was announced by Gautam Adani, the chairman of the Gujarat-based group, while talking to the media after inking the agreement on August 17, 2015.Senior government Ports officials overseeing the Vizhinjam project said they were ‘’brainstorming’’ with the Adani group regarding the options before them. The construction of the breakwater is also expected to resume only when the monsoon rains recede.

For several months now, the construction of the breakwater has not progressed due to a severe shortage in construction rock. So far, only 600 metres of the 3.1 km structure has been completed. Attempts to procure rock from Kanyakumari in Tamil Nadu and Kollam are on, but nothing has been finalised yet. Local consignments keep trickling in, but the demand is to the tune of several lakh tonnes of rock.

The plan now is to use bottom-opening barges to dump the rocks in place after the southwest monsoon. For months now, there were hints the first phase work would go beyond the deadline. On Tuesday, Ports Minister Ramachandran Kadannapally confirmed the fears in the Assembly.

Project TIMELINE

August 17, 2015: UDF Government inks MoU with Adani Group

December 5, 2015: Adani Vizhinjam Port Pvt Ltd starts construction of port

November 30, 2017: Ockhi strikes, damaging dredgers and other equipment

March 6: Ports Minister informs Assembly the project will miss the deadline.

THE NEW INDIAN EXPRESS

Post your comments:

Your name: *
E-Mail Id:
E-mail ID will not be published
Comment: *
Maximum 500 Characters
    
Related Stories
Allcargo Logistics to expand its warehouse capacity
Deendayal Port in Kandla to have fertiliser cargo facility.
Subarnarekha port gets defence ministry nod; construction to begin soon.
Avvashya CCI Logistics plans Rs 60-cr warehouse in Assam
Lenders seek new promoters for the much-delayed Dahej port project.
Centre to decide on new transport arrangement at Jawaharal Nehru Port.
Adani's Dhamra port expansion opens doors to South-East Asia.
KCCI seeks immigration clearance at Old Mangalore Port.
Hopes for Ramayapatnam port brighten.
Trial run at port from tomorrow.
RELATED PROJECTS & TENDERS
ADVERTISEMENT
MOST POPULAR STORIES NOW
For all enquiries please contact
Tel: 022 - 25961254, 25960909
Mobile: 9821464666/09751178830
Mail: marketing@newsonprojects.com

OUR OTHER PRODUCTS & SERVICES:    Projects Database   |   Project e-Newsletter   |   Tenders Database   |   Commissioned Power Plants   |   Company Index
About Us   |   Contact Us   |   Terms of Use   |   Advertise with Us   |   Privacy Policy   |   Disclaimer   |   Feedback