Published On:June 28 2014
Story Viewed 1780 Times

Hyderabad Metro train receive 9 more coaches.

In addition to the first Hyderabad Metro train received last month which is undergoing different tests at Uppal Metro Rail Depot, 3 more trains (each train consisting of 3 coaches) have now reached Uppal depot.

These 3 trains (9 coaches) which arrived at Chennai port from South Korea about 10 days ago were brought to Hyderabad on special multi-wheeled road trailers.

With this, so far 4 of the 7 trains required for Stage-I Metro operations between Nagole and Mettuguda (8 km) have been received. The remaining 3 trains will be received in the next few months.

This is ahead of schedule and gives sufficient cushion for elaborate tests and trial runs for safety certification by Commissioner of Metro Rail Safety. Commissioner of Railway Safety of SC Railway is the CMRS for the Hyderabad Metro project.

Manufacturing of Metro coaches in Hyundai Rotem factory in South Korea for the specific conditions of a city and the prescribed design specifications normally takes 20 to 24 months.

Mr. NVS Reddy MD of HMR said that the Metro trains have been delivered ahead of schedule,

Mr. K.Chandrasekhar Rao CM of Telangana advised the metro team to consult experts and take all safety precautions before starting trial runs.

The Concessionaire L&TMRHL earlier placed an order on Hyundai Rotem of South Korea for 171 coaches (57 trains) at a cost of about INR 1800 crore for the needs of all the 3 Corridors of the project (72km), which is scheduled for completion by June 2017.


STEELGURU


OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software