Published On:August 17 2020
Story Viewed 954 Times

India grants five month extension to renewable project completion.

India has granted five month extension to August 24 to all renewable energy projects that were under implementation on the March 25, when the country went under nearly a seven week complete lockdown, a government statement said on August 14.

"This blanket extension, if invoked by the RE (renewable energy) developers, will be given without case to case examination and no documents/evidence will be asked for such extension," said the statement.

Previously the government had asked developers to produce evidence that delays in meeting completion deadlines are triggered by disruption of the supply chains due to due to spread of coronavirus in China or any other country.

Some of the companies who had won projects between July and August 2018 and had a July 2020 deadline include Aditya Birla Renewables and SoftBank -backed SB Energy, a banking source told Reuters in February.

The timelines for intermediate milestones of a project may also be extended within the extended time provided for commissioning, it said.

 





OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software