"KP Energy Commissions 25.2 MW ISTS Connected Wind Power Project"

"KP Energy Commissions 25.2 MW ISTS Connected Wind Power Project"

KP Energy has achieved yet another milestone by successfully commissioning an additional 25.2MW (Phase-VI) ISTS connected Wind Power Project. This latest phase comprises 12 wind turbine generators (WTGs) of 2.1MW each, located at the Sidhpur site in Devbhoomi Dwarka.

The Phase-VI commissioning is part of the larger 250.8MW ISTS connected Wind Power Project awarded to Apraava Energy Private Limited by Solar Energy Corporation of India Limited (SECI) under Tranche-VIII bidding. KP Energy is executing the project for Apraava Energy Private Limited as a contractor under the Land and Balance of Plant Contract.

With the completion of Phase-VI, the total cumulative capacity commissioned at the Sidhpur site reaches 163.8MW. This includes capacities from previous phases, totaling 52.5MW, 29.4MW, 25.2MW, 21MW, and 10.5MW respectively. This significant achievement contributes towards fulfilling the awarded capacity of 250.8MW for the project.

EQUITYBULLS





OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2024

Technology Partner - Pairscript Software