NGT clears decks for Hubli-Ankola rail line.
Decks have been cleared for the controversial Hubli-Ankola railway line, cutting across the eco-sensitive Western Ghats in Karnataka, with the National Green Tribunal giving its nod to Railways to approach the State government.
The order assumes significance as the Supreme Court-appointed Central Empowered Committee (CEC) last year had disapproved the 168-km rail link project, conceived in 1998 primarily to transport iron ore from the Bellary-Hospet mines, and said that it would have 'huge and irreparable” ecological impact on the forests, wildlife and biodiversity of the Western Ghats.
The controversy in the present case relates to conversion of forest land to a non-forest activity (construction of broad gauge railway line) for which total land of 965 hectares falling in Dharwad, Yellapur and Karwar forest divisions in Karnataka was required.
The green panel said that to apply for conversion of forestland to a non-forest activity was a right available to the project proponent and the State government, which has to be dealt with in accordance with law.
'Under the provision of Section 2 of Forest (Conservation) Act, 1980 the State Government has to issue an order permitting such conversion with prior approval of the Central Government that is MoEF. We do not think that CEC even intended to allow or deny such right to the Project Proponent (Railways) but has expressed its view for non grant of such permission in terms of Section 2 of the Forest (Conservation) Act, 1980,' a bench headed by NGT Chairperson Justice Swatanter Kumar said.