NTPC commissions Unit 2 of 800MW capacity of Gadarwara project.
Based on achievement of approved norms, Unit-2 of 800 MW capacity of Gadarwara Super Thermal Power Project has successfully completed trial operation and consequently included in the installed capacity of NTPC.
With this, the total installed capacity of NTPC and NTPC group has become 52110 MW and 64875 MW respectively.