Published On:June 25 2019
Story Viewed 1188 Times

Sterlite Power doubles transmission capacity in Lucknow.

Sterlite Power recently said it has uprated and commissioned five 132 kv lines in Lucknow, the Capital of Uttar Pradesh.

Transmission capacity of these five existing lines were doubled without any major change to existing infrastructure, a Sterlite Power statement said. According to the statement, these lines, which normally carry 80-85 MW load, will now be able to carry a load of over 160 MW after the uprate.

“Our solutions of upgrade and uprate of transmission lines solve key constraints around time, space and capital. These solutions have the potential to solve transmission congestion challenges in all states including Uttar Pradesh towards ensuring 24X7 reliable power,” Manish Agarwal, CEO, Solutions Business, Sterlite Power, said.

Sterlite Power is a developer of power transmission infrastructure with projects of over 12,816 circuit kms and 22,044 MVA in India and Brazil.

HBL





OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software