Bid to expedite Hyderabad Metro project.

The Special Task Force on Hyderabad Metro Rail project is seeking to ensure a coordinated work between various departments and agencies to facilitate rapid implementation of the 72-km-long elevated metro rail project.

Nodal officers have been appointed from all government organisations to resolve the issues at the field level.

NVS Reddy, MD, Hyderabad Metro Rail Ltd., said that so far 1,150 foundations (35 km), 1,001 pillars (30 km) and 8,205 segments (sufficient for 25 km) have been completed.

He mentioned that the track laying work in the first stretch of 8 km between Nagole to Mettuguda will be opened for passenger traffic on Ugadi Day in March 2015 as scheduled.

HBL


OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software