Published On:August 5 2019
Story Viewed 1188 Times
Dilip Buildcon Ltd. entitled for bonus of Rs. 38.29 crore for completing project ahead of time.
Dilip Buildcon Ltd. has announced that the project 'Four laning of Yavatmal to Wardha (Package-III) section of NH-361 from Km 400.575 to Km 465.500 (design length 64.925 Km) under NHDP Phase-IV on Hybrid Annuity mode in the state of Maharashtra' has been provisionally completed.
The Provisional Completion Certificate has been issued by the authority and has declared the project fit for entry into operation as on August 02, 2019 and consequently, the Company is entitled to maximum bonus of Rs. 38.29 Cr. in lieu of earlier completion (367 days prior to the schedule completion date) of the said Project.