Published On:March 20 2009
Story Viewed 2524 Times

Mundra power project to generate power in April

Kolkata: Adani Power is expected to generate power from its ongoing 4,620 MW thermal power plant at Mundra next week.

The company plans to light the boiler of a 330 MW unit at Mundra on March 25. Power generation is expected to begin in April.

Once boiler is ignited the unit will start generating steam, which is used for power generation.

Slated to be fully commissioned in 2011, the Rs 19,106-crore project is divided in four phases. In phase-I, the company will commission two units of 330 MW each followed by 2 X 330 MW in phase–II.
Mundra-III (2 X 660 MW) and Mundra IV (3 X 660 MW) are of super critical category and will be completed in 2011.

According to sources, the commissioning of both the units in phase-I may be completed by the second quarter of quarter of 2009-10. Implementation of phase-II units is in an advanced stage.


Post your comments:
E-mail ID will not be published
Maximum 500 Characters
OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software