Published On:October 10 2015
Story Viewed 2111 Times
Jurala Hydel Plant Goes on Stream.
The commercial operation of the second unit of Lower Jurala hydro-electric project (6X40 MW) commenced on October 5.
The commercial operation was officially announced by the TS Genco recently.
The installed capacity test for declaration of commercial operation date (COD) of Unit-2 of Lower Jurala Hydro Electric Project commenced at 12.30 hours on October 5 and completed successfully at 15.30 hours on the same day, according to an official press release by the corporation.
“The average load observed during the test was 40.461 MW and the performance of the unit was found to be satisfactory,” it said.
After the successful completion of the test, Genco declared the commercial operation date (COD) of Unit-2 of Lower Jural Hydero Electric Project with effect from October 5.
Genco added 40 MW to the grid with the COD of Unit-2 and will be in a position to supply additional generation during peak hours and additional water available in the river during the flow.
THE NEW INDIAN EXPRESS