Delhi-Katra Expressway Completion Delayed by a Year: Govt.

Travelers will have to wait at least another year for the seamless Delhi-Katra expressway journey, as the project faces delays. The Ministry of Road Transport and Highways informed Lok Sabha that two key sections of the Delhi-Amritsar-Katra Expressway in Punjab are now scheduled for completion by March 2026, while two additional link roads will be ready by April 2027.

The ₹40,000 crore, 667-km greenfield expressway was originally targeted for completion by late 2023 to cut Delhi-Katra travel time to under eight hours. The National Highways Authority of India (NHAI) had awarded five out of 21 construction packages in March 2021.

The 158-km Haryana stretch is expected to be ready by April 2025, but delays in Punjab due to land acquisition hurdles and contractual issues have pushed back timelines. One 30-km section in Punjab saw its contract terminated due to land acquisition problems. The government stated that work on the affected section will resume once these issues are resolved.

ET





OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2025

Technology Partner - Pairscript Software