Published On:December 4 2025
Story Viewed 515 Times

JK Cement Ltd Commissions 3.3 MTPA Clinker Line 2.

JK Cement Ltd on December 3, 2025, commissioned its 3.3 MnTPA Clinker Line-2, a key milestone in the company’s 6 MnTPA expansion plan approved by its Board of Directors on January 20, 2024.

The expansion plan includes a brownfield increase in clinker capacity by 3.3 MnTPA (Design: 10,000 TPD; Potential: 12,000 TPD) and cement grinding capacity by 3 MnTPA across Panna, Hamirpur, and Prayagraj (1 MnTPA each), along with a greenfield cement grinding facility of 3 MnTPA in Bihar.

With the commissioning of Clinker Line-2, the clinker capacity at JK Cement’s Panna plant has doubled from 3.3 MnTPA to 6.6 MnTPA.





OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software