Published On:December 3 2011
Story Viewed 2615 Times

BHEL bags ArcelorMittal equipment contract from UKraine

BHEL has bagged a Rs 40 crore contract to supply equipment for a captive power plant being set up at global steel giant ArcelorMittal's plant in Ukraine.

BHEL has bagged the contract for supplying the steam turbine generator (STG) package for the captive power project at ArcelorMittal Group's steel plant at Kryviy Rih, in Ukraine, an official statement said.

BHEL's scope of work under this contract involves design, engineering, manufacture, supply and supervision of the erection and commissioning of the 27-MW steam turbine & generator package, including controls and instrumentation (C&I).

The project is to be executed by BHEL within a contractual completion deadline of 18 months. The steam turbine generators and C&I systems are to be manufactured at BHEL's Hyderabad plant and its electronics division in Bangalore, respectively.


OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software